Fabrication Information Tab

WorAC76

This tab contains the fabrication information for the asset.

Fabrication Information tab definitions

Title

Description

Estimated Fabrication Completion Date

Required. Enter the estimated completion date for the asset or select a date using the calendar icon.

Fabrication Estimated Total Amount

Required. Enter the estimated dollar cost of the fabricated asset.

Years expected to retain asset once fabrication is complete

Required. Enter the number of years the organization is expecting to retain the fabricated asset once it has been completed. When the field is populated with 0, it is an indication that the fabricated asset will be sold upon completion and should not be eligible for depreciation. This serves as a reminder to the Capital Asset Office, that when the construction is complete to treat the asset accordingly.

More:

Process Overview